Schedule of Project  

The design team is working to maintain the following schedule for the project. Please note it is subject to change.

Project Schedule:

Preliminary Design - June 2004 - November 2007
Final Design - Winter 2008 - Spring 2012
Utilities & Environmental (incl. Permitting) - Summer 2004 - Spring 2012
Construction – Fall 2012 - Fall 2013
Public Involvement - Summer 2003 - Fall 2013